Discover the Narmada River: history, culture and the valley.Get in touch

Friends of River Narmada

The Indira Sagar Dam: A Major Multipurpose River Valley Project

Indira Sagar Dam is one of the major river valley multipurpose projects constructed across the Narmada River in the district of Khandwa in Madhya Pradesh. This dam project plays an important role in water resources and the generation of hydroelectricity. This project’s main objective is to provide irrigation water, generate electricity, provide water supply and promote regional development.

This helps in improving the economy of Madhya Pradesh. It helps the agricultural sector, electricity generation and water management. The large reservoir also makes this project very important due to the high amount of storage available to be used for various purposes. This is run by the Narmada Hydroelectric Development Corporation (NHDC), which is a joint venture between NHPC Limited and the Government of Madhya Pradesh.

History and Background of the Indira Sagar Project

The Narmada River has always been an important source of water for Madhya Pradesh and neighbouring regions. Recognising its potential for irrigation, electricity generation and water supply, the government planned several major projects along the river. This Project was proposed as one of the important multipurpose projects under the Narmada Valley Development Programme. Its construction work began in 1992 under the Government of Madhya Pradesh.

In August 2000, the Narmada Hydroelectric Development Corporation (NHDC) was established as a joint venture between NHPC Limited and the Government of Madhya Pradesh. NHDC took over the remaining construction work of the Indira Sagar and Omkareshwar projects. The project received approval from the Cabinet Committee on Economic Affairs (CCEA) in March 2002. The hydroelectric power station was commissioned in stages, and its full installed capacity of 1,000 MW was demonstrated on 25 August 2005.

Location and Geographical Features

Indira Sagar Bandh is located near Punasa village in the Khandwa district of Madhya Pradesh, India. It has been constructed on the Narmada River, which is one of the major westward-flowing rivers of the country.

Some important geographical features of the project are:

  • Narmada River
  • Near Punasa village
  • Located in Khandwa district
  • Madhya Pradesh
  • It covers approximately 61,642 square kilometres of area

Objectives and Major Features of the Project

Main objectives are:

  1. Irrigation

One of the main objectives is to provide adequate water supply for agriculture through canals and other irrigation structures.

  1. Electricity

It provides electricity from the flow of water through turbines. This helps to fulfil the power requirement of Madhya Pradesh.

  1. Water Supply

It fulfils water supply requirements for domestic purposes and other beneficial purposes.

  1. Agricultural Development

The availability of irrigation water helps farmers improve agricultural production and reduce their dependence on seasonal rainfall.

  1. Regional Development

The project supports economic growth by improving water availability, electricity supply and infrastructure.

  1. Proper Utilisation of Water Resources

It helps regulate and store the water of the Narmada River for different purposes.

  1. Support for Downstream Projects

The regulated release of water also supports other projects situated downstream along the Narmada River.

Reservoir and Water Storage Capacity

The reservoir is one of the most important components of the Indira Sagar Project. It stores water from the Narmada River and makes it available for irrigation, electricity generation and other purposes. It has a large storage capacity.

The water storage capacity is divided into two major parts:

  1. Live Storage Capacity

Live storage refers to the quantity of water that can be used for purposes such as irrigation, power generation and water supply.

  1. Dead Storage Capacity

This is the volume of water stored below the lowest operating levels of a reservoir. It is generally not available for release from the project outlet.

Hydroelectric Power Generation

Hydroelectric power generation is one of the major purposes of the Indira Sagar Project. The dam uses the energy of stored and flowing water to generate electricity. The power station has an installed capacity of 1,000 MW.

IRRIGATION FACILITIES AND AGRICULTURE

Agriculture plays an important role in the economy of Madhya Pradesh. Many people in the state depend on agriculture as their source of livelihood. However, due to erratic rain patterns, agricultural activities in many areas suffer from a lack of water.

The Indira Sagar Bandh helps address these problems by providing irrigation facilities through its canal network. The irrigation facilities benefit farmers by providing water for crop cultivation and reducing their dependence on monsoon rainfall.

Major Benefits for Agriculture Include:

  • Improved availability of water for agricultural activities.
  • Reduction in dependence on seasonal rainfall.
  • Support for multiple cropping where water availability permits.
  • Improvement in agricultural productivity.
  • Better utilisation of agricultural land.
  • Support for the economic development of rural communities.

Economic Importance and Regional Development

The Indira Sagar Dam plays an important role in the economic development of Madhya Pradesh.

  1. Growth of Agriculture

Irrigation water is available for farming activities. This leads to enhanced crop production and helps rural communities.

  1. Power Generation

This hydroelectric power station provides electricity to Madhya Pradesh, providing electricity for domestic, commercial and industrial activities.

  1. Employment Opportunities

The construction, operation and maintenance of the dam create employment opportunities for engineers, workers, technicians and other professionals.

  1. Industrial Development

Improved supply of electricity and water can help industrial development and other economic activities.

  1. Rural Development

Improved irrigation and water facilities will lead to improved village and surrounding area development.

  1. Tourism and Fishing

It will allow for fishing and water-based recreation with a large lake. It depends on local regulations and facilities.

  1. Economic benefit to the State

Electricity will be produced to help the economy of the state. Improvement in agriculture and infrastructure.

Environmental Impacts

  1. Submergence of Land

The creation of a large reservoir leads to the submergence of land, including agricultural areas, forests and other natural resources.

  1. Impact on Wildlife

Changes in natural habitats can affect the movement and survival of wildlife in the surrounding areas.

  1. Changes in River Flow

The construction of a dam regulates the natural flow of the river, which can affect downstream ecosystems.

  1. Affect on Aquatic Species

Changes in water flow, temperature and sediment can affect the local fish population.

  1. Changes in Local Area

Creating a large reservoir will have an effect on the local area, including land usage, local plants and ecology.

Social

  1. Effect on Families

Some families in the area will have been forced to move out of their homes.

  1. Affecting Farming Areas

The farming areas will have been affected due to being underwater.

  1. Affecting Traditional Incomes

Those who work within the local area, such as farming and fishing, will see changes in their income.

  1. Impact on Community

Displacement may impact traditional relationships, cultural activities and local infrastructure.

Issues, Displacement & Resettlement

Below are some of the key difficulties of the project.

  1. Affecting Families

The creation of the reservoir has affected local communities & families, as those living in the area were displaced for the development. Moving can create problems for those who have strong social, economic, and cultural ties to their original village.

  1. Resettlement and Rehabilitation

Finding appropriate housing, compensation, farming land, and basic facilities for the affected families will be an issue. Proper rehabilitation will be required for the families.

  1. Environmental Issues

The land being underwater and changes to the river ecosystem can cause environmental issues. Constant care must be taken to protect the local forest, wildlife & aquatic species.

  1. Land Purchase

Land may need to be purchased for the dams, canals and other infrastructure. This can be a complex process involving multiple communities & landowners.

  1. Water Management

Proper planning is required to manage the available water to irrigate, generate electricity, etc.

  1. Maintenance

The dam, spillways, power station and canals must be regularly checked & maintained to ensure they are safe in the long term.

Resettlement

Rehabilitation and resettlement are important aspects when addressing these issues. This could include:

  • Compensation for the land and property that has been acquired.
  • Providing adequate housing.
  • Provision of clean drinking water, electricity and sanitation.
  • Education and healthcare services.
  • Support in getting back into agricultural and other activities.
  • Proper planning and monitoring of rehabilitation policies.

Conclusion

The Indira Sagar Dam is one of the most important multi-purpose river valley projects in India. It is built across the Narmada River in the Khandwa district of Madhya Pradesh. It plays a crucial role in irrigation as well as hydroelectric power generation.

The project has a total capacity of 1000 MW. It has a storage capacity of around 12.22 billion cubic meters. Hence, it has become an important part of the state’s infrastructure. It helps boost agriculture, increase the availability of electricity, boost the economy of the region and help make optimal use of the water resources of the Narmada River.

There are various environmental and social issues associated with this project. This is because the Dam causes land to be submerged, which means many families have been displaced and need rehabilitation.

FAQs

1. Where is Indira Sagar Dam located?

It is located very near Punasa village in Khandwa district of Madhya Pradesh, India.

2. On which river is Indira Sagar Dam constructed?

It is constructed on the Narmada River.

3. When was the construction of Indira Sagar Dam started?

The construction work of Indira Sagar Dam started in 1992.

4. When was Indira Sagar Dam commissioned?

The hydroelectric power plant achieved full capacity in August 2005. It was commercially commissioned in May 2005.

5. What is the power generating capacity of the dam?

The total installed capacity of Indira Sagar Dam is 1000 MW, with eight units of 125 MW each.